Spring Khola Hydroelectric project
Project Type

Hydro Power

Client

Syenergy Power Development Ltd.

Scope of Work

Tunneling work and concreting work of settling basin

Project Start Date

---

Project End Date

27 Aug, 2012

Spring Khola Hydroelectric project


The Siprin Khola Hydroelectric Project, focusing on its hydrology at the intake, boasts a design discharge of 2.61 m3/s. Transitioning to the powerhouse, the design head is an impressive 443.7 m, showcasing the project's capacity for efficient energy generation. In terms of waterways, the penstock spans a length of 649.22 m, exhibiting a dynamic diameter that varies from 1.2 m at the upstream end to 0.9 m at the downstream. The project's turbines are Pelton turbines with a horizontal shaft arrangement, a design chosen for optimal energy conversion. The powerhouse integrates two such turbines, emphasizing the project's commitment to harnessing the potential of Siprin Khola for sustainable hydroelectric power generation.